+ | ==Building a bill of materials (BOM)== | ||
+ | Your project BOM will include all components necessary to build your <u>final</u> product. You won't be able to do this properly without a good detailed design so that you don't miss any items. Imagine someone else is tasked with rebuilding your product, they need to be able to do so with whatever is specified in the BOM. Based on that list you will also be able to tally your total product cost. | ||
+ | |||
+ | ===Bill of materials=== | ||
+ | The most efficient way of compiling your BOM is in a tabular format. Here are the columns that should be included with a few examples of items: | ||
+ | {| class="wikitable" | ||
+ | |+ | ||
+ | !Item name | ||
+ | !Description | ||
+ | !Units of measure | ||
+ | !Quantity | ||
+ | !Unit cost | ||
+ | !Extended cost | ||
+ | !Link | ||
+ | |- | ||
+ | |Screw | ||
+ | |M3 x 8mm | ||
+ | |Unit | ||
+ | |4 | ||
+ | |0.1$ | ||
+ | |0.4$ | ||
+ | |https://edu-makerlab.odoo.com/shop/product/socket-head-screw-metric-70?search=screw#attr=375,370 | ||
+ | |- | ||
+ | |Wire (5 ft) | ||
+ | |22 awg, red | ||
+ | |Unit | ||
+ | |1 | ||
+ | |2.5$ | ||
+ | |2.5$ | ||
+ | |https://edu-makerlab.odoo.com/shop/product/wire-5ft-45?search=wire#attr=213,217 | ||
+ | |- | ||
+ | |NewPing library | ||
+ | |For ultrasonic sensors | ||
+ | |Unit | ||
+ | |1 | ||
+ | |0$ | ||
+ | |0$ | ||
+ | |https://www.arduino.cc/reference/en/libraries/newping/ | ||
+ | |- | ||
+ | |Weather API | ||
+ | |Get forecasts for different cities | ||
+ | |Unit | ||
+ | |1 | ||
+ | |0$ | ||
+ | |0$ | ||
+ | |https://rapidapi.com/community/api/open-weather-map | ||
+ | |- | ||
+ | | colspan="5" |'''Total product cost (without taxes or shipping)''' | ||
+ | |2.9$ | ||
+ | | | ||
+ | |- | ||
+ | | colspan="5" |'''Total product cost (including taxes and shipping)''' | ||
+ | |3.28$ + 0$ shipping | ||
+ | | | ||
+ | |} | ||
+ | There are things that you will often forget about when putting this list together, here are some tricks: | ||
+ | |||
+ | #Don't forget to add links to each item | ||
+ | #Don't forget the taxes | ||
+ | #Don't forget the shipping cost | ||
+ | #Don't forget to include costs of 3D printing or laser cutting materials, estimates can be found from https://makerepo.com/print_orders/index_new | ||
+ | #Include ALL items, even if they are 0$ | ||
+ | |||
+ | ===List of equipment=== | ||
+ | You may have other items that are necessary to test your different prototypes however. For example you may need a breadboard to test a prototype but that will not be included in the final product, the breadboard would then be included in your list of equipment but not your bill of materials. Your list could look something like this: | ||
+ | {| class="wikitable" | ||
+ | |+ | ||
+ | !Item name | ||
+ | !Description | ||
+ | !Type | ||
+ | !Prototype # | ||
+ | !Source | ||
+ | |- | ||
+ | |Drill press | ||
+ | |To drill holes in base | ||
+ | |Equipment | ||
+ | |3 | ||
+ | |Brunsfield | ||
+ | |- | ||
+ | |Breadboard | ||
+ | |To test circuit | ||
+ | |Temporary material | ||
+ | |2 | ||
+ | |MakerLab | ||
+ | |- | ||
+ | |Android studio | ||
+ | |To build app | ||
+ | |Software | ||
+ | |2,3 | ||
+ | |https://developer.android.com/studio | ||
+ | |} | ||
+ | |||
==Spending your Project Budget== | ==Spending your Project Budget== | ||
− | #Before anything is bought by your team, a PM or TA must approve it. | + | #Before anything is bought by your team, a PM (project manager) or TA (teaching assistant) must approve it. |
#When reviewing BOMs always check for: | #When reviewing BOMs always check for: | ||
##Complete list of parts, this should be representative of the designs and include fasteners and wire and everything else. | ##Complete list of parts, this should be representative of the designs and include fasteners and wire and everything else. | ||
Line 8: | Line 100: | ||
##If a cheaper supplier exists. | ##If a cheaper supplier exists. | ||
#When looking for places to find parts, here is the order of places to look: | #When looking for places to find parts, here is the order of places to look: | ||
− | ##In the Makerlab | + | ##In the [http://inventory_mlab.makerepo.com/ '''Makerlab'''] (cost included in BOM). |
− | ##In the [https://makerstore.ca/ Makerstore] (cost included in BOM). | + | ##In the [https://makerstore.ca/ '''Makerstore'''] (cost included in BOM). |
##Online or local stores, some common places are below. | ##Online or local stores, some common places are below. | ||
Line 32: | Line 124: | ||
*'''Digikey''' https://www.digikey.ca/ | *'''Digikey''' https://www.digikey.ca/ | ||
*'''Robotshop''' https://www.robotshop.com/ca/ | *'''Robotshop''' https://www.robotshop.com/ca/ | ||
+ | *'''Simcoe DIY''' https://www.simcoe-diy.ca/ | ||
*'''Great Hobbies''' https://www.greathobbies.com/ | *'''Great Hobbies''' https://www.greathobbies.com/ | ||
*'''Sparkfun''' https://www.sparkfun.com/ | *'''Sparkfun''' https://www.sparkfun.com/ | ||
Line 38: | Line 131: | ||
*'''A2D electronics (local)''' https://a2delectronics.ca/ | *'''A2D electronics (local)''' https://a2delectronics.ca/ | ||
*'''Electronics shop (local- in STEM!)''' https://science.uottawa.ca/en/faculty-services/electronics-shop (they don't have an inventory on the website but if you go see them they have things they can give you) | *'''Electronics shop (local- in STEM!)''' https://science.uottawa.ca/en/faculty-services/electronics-shop (they don't have an inventory on the website but if you go see them they have things they can give you) | ||
+ | |||
+ | === Other === | ||
+ | |||
+ | * '''ReFasten''' https://refasten.ca/ (recycled fabrics, zippers, and hardware generally used to create outdoor gear) |
Latest revision as of 21:00, 2 March 2022
Building a bill of materials (BOM)
Your project BOM will include all components necessary to build your final product. You won't be able to do this properly without a good detailed design so that you don't miss any items. Imagine someone else is tasked with rebuilding your product, they need to be able to do so with whatever is specified in the BOM. Based on that list you will also be able to tally your total product cost.
Bill of materials
The most efficient way of compiling your BOM is in a tabular format. Here are the columns that should be included with a few examples of items:
Item name | Description | Units of measure | Quantity | Unit cost | Extended cost | Link |
---|---|---|---|---|---|---|
Screw | M3 x 8mm | Unit | 4 | 0.1$ | 0.4$ | https://edu-makerlab.odoo.com/shop/product/socket-head-screw-metric-70?search=screw#attr=375,370 |
Wire (5 ft) | 22 awg, red | Unit | 1 | 2.5$ | 2.5$ | https://edu-makerlab.odoo.com/shop/product/wire-5ft-45?search=wire#attr=213,217 |
NewPing library | For ultrasonic sensors | Unit | 1 | 0$ | 0$ | https://www.arduino.cc/reference/en/libraries/newping/ |
Weather API | Get forecasts for different cities | Unit | 1 | 0$ | 0$ | https://rapidapi.com/community/api/open-weather-map |
Total product cost (without taxes or shipping) | 2.9$ | |||||
Total product cost (including taxes and shipping) | 3.28$ + 0$ shipping |
There are things that you will often forget about when putting this list together, here are some tricks:
- Don't forget to add links to each item
- Don't forget the taxes
- Don't forget the shipping cost
- Don't forget to include costs of 3D printing or laser cutting materials, estimates can be found from https://makerepo.com/print_orders/index_new
- Include ALL items, even if they are 0$
List of equipment
You may have other items that are necessary to test your different prototypes however. For example you may need a breadboard to test a prototype but that will not be included in the final product, the breadboard would then be included in your list of equipment but not your bill of materials. Your list could look something like this:
Item name | Description | Type | Prototype # | Source |
---|---|---|---|---|
Drill press | To drill holes in base | Equipment | 3 | Brunsfield |
Breadboard | To test circuit | Temporary material | 2 | MakerLab |
Android studio | To build app | Software | 2,3 | https://developer.android.com/studio |
Spending your Project Budget
- Before anything is bought by your team, a PM (project manager) or TA (teaching assistant) must approve it.
- When reviewing BOMs always check for:
- Complete list of parts, this should be representative of the designs and include fasteners and wire and everything else.
- Shipping and tax costs, duties can be expensive so try to buy things from Canada.
- If a cheaper or better alternative exists.
- If a cheaper supplier exists.
- When looking for places to find parts, here is the order of places to look:
- In the Makerlab (cost included in BOM).
- In the Makerstore (cost included in BOM).
- Online or local stores, some common places are below.
Online and Local Stores
General
- Amazon https://www.amazon.ca/
- Science store (local- in STEM!) https://science.uottawa.ca/en/faculty-services/store
Mechanical/hardware
- SDP/SI https://www.sdp-si.com/
- Spaenaur (Canada) https://spaenaur.com/
- McMaster-Carr (US) https://www.mcmaster.com/
- Hardware stores (local) home hardware, home depot, rona
- Metal Pros (local) http://www.metalpros.com/
- MetalMart (local) https://www.metalmart.ca/
Electrical/robotics
- Digikey https://www.digikey.ca/
- Robotshop https://www.robotshop.com/ca/
- Simcoe DIY https://www.simcoe-diy.ca/
- Great Hobbies https://www.greathobbies.com/
- Sparkfun https://www.sparkfun.com/
Active tech electronics(Merged with Gervais)- Gervais electronics (local) http://www.gervaiselectronics.ca/
- A2D electronics (local) https://a2delectronics.ca/
- Electronics shop (local- in STEM!) https://science.uottawa.ca/en/faculty-services/electronics-shop (they don't have an inventory on the website but if you go see them they have things they can give you)
Other
- ReFasten https://refasten.ca/ (recycled fabrics, zippers, and hardware generally used to create outdoor gear)